Gravel & Paver Base Calculator

Area and depth in; yards and tons out — with the compaction extra a base course really takes, and a paver mode that builds the standard base-plus-bedding-sand stack for you.

Order

—

Enter the area and a depth.

How much gravel do I need?

Area × depth ÷ 324 gives cubic yards, same as mulch — but gravel is sold by the ton as often as by the yard, and a base course compacts: run a plate compactor over crusher run and it loses about 15% of its loose volume, which is volume you have to order. The calculator converts both ways using each material's real density and adds the compaction allowance where the material needs one.

Yards = area × depth ÷ 324; tons = yards × density ÷ 2,000; ÷ (1 − compaction) for base

A 300 sq ft patio's 4-inch base course is 3.70 yd compacted — order 4.36 yd loose, which is 6.3–7.0 tons of crusher run. The inch of bedding sand on top is 1.03 yd (1.3–1.5 tons).

Gravel weight: tons per cubic yard

MaterialTons per yardCompactionUse
Crusher run / road base (¾″ minus)1.45–1.6015%Fines + angular stone; locks solid. The paver base layer.
Clean crushed stone (#57, ¾″)1.35–1.455%No fines; drains. French drains, driveways over base.
Pea gravel1.30–1.405%Rounded; never locks. Paths and dog runs, not base.
River rock / decorative1.20–1.350%Ground cover over fabric; order by looks, not layers.
Concrete / bedding sand1.30–1.5010%The 1″ screeded layer under pavers.
Decomposed granite1.30–1.4512%Compacts to a firm path surface.

Supplier-published densities; moisture moves them a few percent. A ton of most gravel is about ⅔ of a cubic yard.

Crusher run and clean stone are not interchangeable

"Crusher run" (¾″ minus, road base, ABC — the names vary by region) contains stone dust that locks the angular pieces together when compacted; it's what patios, sheds and driveways sit on. "Clean" stone has no fines, stays loose, and drains — which is exactly why it goes in French drains and why a patio built on it shifts. Pea gravel is round and never locks at all: fine for a path, hopeless as base. Buy the boring gray one for structure and the pretty one for the top inch.

The paver base build-up

The industry-standard stack under concrete pavers, per ICPI guidance: compacted crusher-run base — 4 inches for patios and walks, 8 for driveways, plus a couple of inches on clay or soft soil — then one inch of bedding sand, screeded flat, never compacted, never deeper (thick sand ruts). Geotextile fabric between soil and base is cheap insurance on clay. Excavate base + sand + paver thickness below finished grade, compact the subgrade, then build up in 2-inch lifts, compacting each. The paver mode above sizes both layers and the digging.

Coverage: how far a yard goes

Depth1 cu yd covers
2 in162 sq ft
3 in108 sq ft
4 in81 sq ft
6 in54 sq ft

Loose volume, before compaction. For decorative rock over fabric, 2 in hides the fabric; 3 in stays hidden after the dog.

Ordering and moving it

Gravel yards sell by the ton or the yard — give them square feet and depth and they'll quote either; the calculator's tons figure lets you sanity-check the quote. A ton of gravel is one scoop of a small loader and about the legal payload of a half-ton pickup (which is why the truck is called that — don't put a yard and a half in it). For anything over a few tons, delivery is cheap next to a chiropractor. A wheelbarrow holds about 6 cu ft, so a yard is roughly 4–5 loads; a 300 sq ft patio's base is 20 of them.

Sources: ICPI (Interlocking Concrete Pavement Institute), Residential Paver Installation Guide (base and sand thicknesses); supplier published aggregate densities; NRCS compaction factors for crushed aggregate. Names for ¾″-minus base vary regionally — crusher run, road base, ABC, QP, dense-grade.